Important Exterior Project – Update 2
August 7, 2009 by Howard Olsen · 2 Comments
Our best tentative schedule at the moment for the work scheduled is as follows:
On the Solo building, we will probably still be on the north side of the building for 3-4 weeks, and on the south side of the building for approximately 3-4 weeks after that.
On the Duo building, we are underway, and are probably 4-5 weeks on that building.
We will start the Treo building as we are wrapping up the Duo building, and it will probably be commenced in 4-5 weeks time.
All of this is weather dependent, and is a tentative schedule at the best. We will always be giving owners advance notice of when we need to have balconies cleared, etc. I attach for you a copy of the notice that we drop off to the owners.
Please call me if you have any questions or comments.
Regards,
Maurice F. Hulscher
President, Alumni Restorations Ltd.